"This spring marks three years of construction! We share your sense urgency to get things wrapped up and are excited to report we can see the light at the end of the tunnel." Lennar opened its April 20, 2026 construction update for The Trails at Carmel Mountain Ranch with that line, and Lennar's own wording leaves out a word.
That light has a set order. The former golf course is opening to the public in sequence. Three small city parks come first, and they are being built to a fixed budget that has already cut some features. The roughly five-mile trail network that runs through the neighborhood comes after them. Most of that network is the old concrete cart paths. Councilmember Marni von Wilpert's office stated the order plainly at the June 10, 2026 meeting of the Carmel Mountain Ranch/Sabre Springs Community Planning Group: "The neighborhood parks will be built first, with the trail system completed after the neighborhood parks are completed."
The Order Things Have to Happen In
The project's own documents lay out the steps:
- Park permitting and construction. Gafcon manages construction of all three public parks. At the April 8 planning group meeting, Gafcon's Chris Larson presented a revised schedule alongside three City of San Diego representatives.
- Parks go to the City. The City's 2021 planning report specifies that the parks are dedicated to the City and maintained by it.
- Trail inspection. Lennar says "a public use easement will be recorded over all trails once they have been inspected."
- The trails become publicly accessible. The trails stay privately owned, and the recorded recreation easement is what makes them public.
Step four depends on paperwork. The trails become public through a recorded easement after inspection. Until then, they are not public trails in the legal sense the project approval set up.
Three Parks, Three Different Sizes and Feature Lists
Together the three parks cover 7.87 net acres, according to the City's planning report. How that acreage is split, and what goes on each site, is different from park to park. The feature lists and statuses below come from Gafcon's April 8, 2026 slides. The start dates come from Lennar's April 20 email.
| Park | Street | Net acres | Planned features, April 2026 | Status, April 2026 | Tentative construction start |
|---|---|---|---|---|---|
| Eastbourne Park, Unit 16 | Carmel Ridge Road | 2.59 | Open green space, accessible walking paths, benches, picnic tables, water fountain | Permitting | April 2026 |
| Walden Park, Unit 13 | Esprit Avenue | 1.9 | Passive open space, playground, water fountain, benches, accessible sidewalk | Redesign | September 2026 |
| Shoal Creek Park, Unit 7 | Shoal Creek Drive | 3.38 | Passive open space, water fountain, benches, accessible sidewalk | Redesign | November 2026 |
The table shows a mismatch between size and features. Shoal Creek is the largest site at 3.38 acres, and it has the shortest feature list, with no playground and no picnic tables, and the latest start date. Walden is the smallest at 1.9 acres and is the only one of the three with a playground in the April slides. Eastbourne is the only one with picnic tables. In March, the planning group chair reported that Eastbourne was scheduled to be completed first.
Every date in that last column is a start date. None of the 2026 materials give a completion date for any of the three parks. Lennar's update says its dates reflect "the project status at the time of publication and are subject to change." As of October 6, Walden's tentative start month has passed and Shoal Creek's is next month. No public update since April confirms that work started at any of the three sites.
What the Budget Cut, and What Was Left in the Ground
The April 8 minutes record the reason the two later parks show "Redesign." Because construction costs rose, "some of the park features will be removed from the plan to remain within the original budget."
Lennar's email describes the same decision and adds a detail the minutes leave out:
"The project team has worked within the established maximum cost provisions for The Trails approvals to keep the parks moving forward. As a result, some features have been deferred for now. Importantly, key underground infrastructure, including water and sewer, has already been extended into the park sites, positioning the park to easily accommodate additional amenities in the future as funding allows."
This explains why the first parks will be smaller than the original plan. The project's approvals cap park spending, so higher costs led to cutting features rather than adding money. The water and sewer lines already run to the sites, so the deferred features have utility connections in place. The email does not say what will fund them later. "As funding allows" is the only timeline it gives.
The deferral also affects the roads nearby. Lennar says road restoration across the project was underway in April and expected to take 8 to 12 weeks. Restoration around the future public parks, however, "will be done when construction of those areas is complete." Streets next to a park that starts in November will stay in construction condition longer than the rest of the neighborhood.
Shoal Creek Drive has had more scrutiny than the other park streets. At the April meeting, attendees were told a 2024 traffic study found that traffic regulation near the planned Shoal Creek Park was not necessary. By June, Councilmember von Wilpert's office had sent a memo to the Mayor's office, the city transportation department and customer services recommending a 4-way stop at Shoal Creek Drive and Windcrest Lane.
The Trail Network Is Mostly the Old Cart Paths
The trails come after the parks, and most of the trail network already exists. The City's planning report says most of the system reuses the former golf-cart paths. New segments crossing the new development areas use decomposed granite or concrete. The City Council resolution describes the network as about five miles long and 5 to 8 feet wide, connecting to sidewalks on the new internal streets and on existing neighborhood streets.
Lennar's approved trail map, dated October 3, 2022, divides the network into three classes. The recreation easement covers all three:
- Existing trail. Concrete golf-cart paths on the site, with slopes steeper than ADA accessibility requirements allow.
- Existing off-site trail. The same kind of concrete cart path, located off the project site.
- Proposed new trail. Concrete, at least 5 feet wide, built to accessible-route standards.
The map also marks a pedestrian tunnel for trail connections. Lennar's April email says the steeper sections will stay as they are. "Existing trails will not be modified so safety signage will be installed on segments that are not ADA compliant." On the finished network, the new pieces will be accessible paths, and much of the rest will be the old cart-path grades with warning signs.
The project's design guidelines describe the trails as linking the commercial centers on the north side with the Carmel Mountain Ranch Recreation Center and Park and with the Sabre Springs–Peñasquitos Rapid Transit Station. The guidelines also list Chicarita Creek among the open spaces the project preserves. Those connections will be public only after the parks are finished and the easement is recorded.
The approval documents name the trails' owner, but it is less clear who will run them day to day after construction. At the March 11 meeting, the planning group was told Lennar was still operating The Trails HOA and was the contact for its common areas while construction continued.
Where the Next Status Report Comes From
Lennar's CMR updates page says updates have moved from monthly to quarterly. Its newest entries are still the April 20 email and the April 8 slides. The planning group has kept the subject on its agenda. The August 12 agenda listed "New CMR Trails" and the September 9 agenda listed "CMR Trails" under old business. The City's planning group page shows the July 8 meeting as adjourned, and June 10 was the latest set of minutes posted when this research was done.
The next regular meeting is Wednesday, October 14, 2026, held online. The September agenda lists the Council District 5 representative as a standing item, and that representative has delivered the Trails updates at past meetings. At that meeting, the public should get answers on whether Eastbourne broke ground, whether Walden started in September, and whether Shoal Creek is still set for November.
If you own a home along the old fairways and want to know how a finished park or a recorded trail easement nearby could figure into your home's value, Karlee Van Dyke follows these Carmel Mountain Ranch updates closely and can walk you through it. Get Your Free Home Valuation, and we will include what the latest Trails schedule means for your street.